October 29, 2026
The replacement for the power line under Leetsdale Drive won't follow Leetsdale Drive. It is going in under South Hilltop's residential streets one block at a time, and that decision explains almost everything about the barricades on Cedar, Ellsworth and Glencoe this fall.
The project is Xcel Energy's Leetsdale-Monroe-Elati 230-kilovolt underground transmission line replacement, a six-mile cable running through central and southeast Denver. The Hilltop Neighborhood Association told its members early on that the work "directly effects residents who live in South Hilltop." A year after construction began, the work is still moving through that part of the neighborhood, and it follows a pattern you can plan around.
The existing cable runs mostly beneath Leetsdale Drive and Speer Boulevard. On its project page, Xcel says it can't rebuild the line in place, for three reasons: crews would be working in heavy traffic, the old line has to stay energized while the new one is built, and the work needs more underground space than those corridors have. The new route deliberately avoids collector roadways and the busiest thoroughfares.
Keeping the line off Leetsdale puts it under quieter streets, and that changes what construction looks like there. A crew on an arterial can keep a lane open. A crew on a residential block often can't. In its November 2025 open house Q&A, Xcel explained that each underground vault has to fit around the water, sewer and gas lines already in the street, and those rarely sit in a consistent spot. Because the company can't promise the vault will end up on one side of the road, it plans to close the entire block from both directions while it works.
The tradeoff is time. Xcel says an average closure lasts one to three weeks per block. In practice that means a full closure on your block for a few weeks, followed by the same closure one street over. The crews use the open-trench method: they cut and remove the pavement, dig a trench, and set the new cable and precast vaults inside it.
Cedar has carried the most work so far. Minutes from Denver's District 5 community cabinet meeting on April 7, 2026 recorded that the project's main impact in the district up to then had been in Hilltop along Cedar. The fall schedule keeps the crews nearby. Here is Xcel's Phase 1 closure list as of its schedule update on October 21, 2026, at 2 p.m.
| Street | Segment | Posted window |
|---|---|---|
| E. Bayaud Ave. | S. Clermont St. to S. Bellaire St. | Oct. 15 to Oct. 29 |
| S. Birch St. | E. Cedar Ave. to E. Ellsworth Ave. | Oct. 15 to Oct. 29 |
| E. Cedar Ave. | S. Glencoe St. to S. Fairfax St. | Oct. 21 to Nov. 11 |
| S. Glencoe St. | E. Cedar Ave. to E. Alameda Ave. | Oct. 21 to Nov. 11 |
| E. Ellsworth Ave. | S. Colorado Blvd. to S. Birch St. | Oct. 26 to Nov. 16 |
| E. Ellsworth Ave. | S. Colorado Blvd. to S. Monroe St. | Oct. 26 to Nov. 16 |
| S. Glencoe St. | E. Alameda Ave. to E. Dakota Ave. | Oct. 28 to Nov. 16 |
| E. Dakota Ave. | S. Glencoe St. to S. Holly St. | Oct. 28 to Nov. 16 |
By the first week of November, the posted Bayaud and Birch windows have ended, and the Cedar and northern Glencoe windows run through November 11. Ellsworth is the longest active stretch on the list, with a window from Colorado Boulevard to Birch that runs through November 16. Just south of Alameda, Glencoe and Dakota between Glencoe and Holly have windows ending the same day.
Xcel publishes these as planned windows and says they can shift with the weather, material availability, or something unexpected underground. The project page asks people directly affected to check back weekly for the latest schedule. You can also email [email protected] to join a list for the weekly construction notices.
Xcel built its process around the whole-block closure. In order, it described the steps in the Q&A and on the project page:
The paving step is the easiest one to miss. A block can look finished after the trench is filled, then close again for paving.
Bayaud shows how this plays out with bike routes. When the neighborhood association posted its May 1, 2026 update, it listed the Bayaud closure between Clermont and Bellair as including the Bayaud Cycleway. In the Q&A, Xcel said its routing avoids city-marked dedicated bike lanes, that some Denver routes are marked with arrows rather than as dedicated lanes, and that the City can require detours for bike paths as part of its right-of-way permit. Xcel has also committed to restoring any sidewalk it disturbs to its previous condition and to ADA standards.
Full-block closures on residential streets get in the way of routines Leetsdale Drive never touched, such as trash day, charging the car, or working from home. Xcel has set up specific help for each.
Trash pickup. Xcel says it is working with Denver Waste Collection to keep pickup on schedule. On collection day, crews may move carts to one side of the street for the truck and will help bring them back to your property if they had to move them.
EV charging. Xcel has added a mobile EV charging pilot for eligible residents whose usual charging spot is blocked by construction. It asks for seven days' notice when possible, although shorter requests may work depending on conditions and equipment, and participants sign a waiver before using the mobile unit. Xcel posted the program notice in October. If your block shows up on the schedule, the time to call is when the door hanger arrives, not when the barricades go up.
Midday trips. If you work from home but need to leave during work hours, Xcel says it will try to accommodate access requests made ahead of time, either through the project contacts or with the crew on site.
Property damage. Xcel's contractors repair private property damaged during the work through a claims process. You can start one by email, by phone, or by telling the on-site crew, and BT Construction handles the claim with the owner.
The same contacts cover all four: (303) 716-8990 and [email protected].
Phase 1 starts at the Leetsdale substation in the southeast corner of the route and runs northwest toward the Monroe substation. The Phase 1 streets named in the Q&A include South Ivy Street, East Virginia Avenue and South Jersey Street along with the Hilltop streets above. Xcel's current page dates Phase 1 from November 2025 to spring 2027.
Phase 2 runs from Monroe to Elati and has already started north of Hilltop. Its October 21 schedule lists East 4th Avenue between Fillmore and Clayton streets, including the Detroit intersection, through November 6, and Monroe Street between East 1st and East 3rd avenues, including the 2nd Avenue intersection, through October 30. Xcel has said Phase 2 depends on when the City issues permits and probably won't proceed in a straight line. Its posted dates are August 2026 to spring 2028, and the project timeline puts the new line in service in 2028.
For South Hilltop, the remaining Phase 1 window runs to spring 2027. Between now and then, Xcel's weekly schedule is the most reliable way to know whether your block is next.
If your street is on Xcel's list and you're thinking about timing a sale or a move around the work, I'm happy to look at the schedule with you block by block. Work with Debbie Niedergerke. Let's connect about your next move.